D4.1 | Roll out plan for synthesis of energy harvesting value chain-choices and methods and people | M2 | 3; PUM |
D4.2 | Finalization of nanomaterial management and administrative plan (handbook) for operating quality processes for synthesis of nanomaterials (agreement between Manager and WP4) | M4 | 1; UCD |
D4.3 | Implementation of synthetic strategy for early initial value chains etc | M6 | 4; EPFL |
D4.4 | Updating of the choice of nanomaterials (derived from VCAC) | M12 | 3; PUM |
D4.5 | Intermediary report on synthetic methods, characterisation protocols and production delivered by WP leader, Deputy, Project Manager and Administrator. For the production, information will be provided on amount produced and by whom, as well as amounts delivered to which partner and for which task. This report will be annexed to the first periodic report | M12 | 2; ICN |
D4.6 | Report on audit quality and round robin processes (synthesis) for partners in WP4 | M20 | 1; UCD |
D4.7 | Report by WP leader, Deputy and Manager in functioning of WP in relation to quality and timeliness of delivery | M18 | 2; ICN |
D4.8 | Intermediary report on synthetic methods, characterisation protocols and production delivered by WP leader, Deputy, Project Manager and Administrator. Follow-up to D4.5. This report will be annexed to the second periodic report | M30 | 3; PUM |
D4.9 | Final report on synthetic methods, characterisation protocols and production delivered by WP leader, Deputy, Project Manager and Administrator. Follow-up to D4.5 and D4.8. This report will also be annexed to the final report | M40 | 3; PUM |